About This Project

Industry Civil

Budget

$1.2M

Contract

2020

Location

Old Bar

Overview

Goldspring was awarded the contract to upgrade the out-dated intersection of Old Bar Road and Saltwater Road. The project involved shoulder widenings, insitu pavement stabilisation and deep lift asphalt. Project was completed 4 weeks ahead of schedule, which minimised disturbance on the extremely busy Old Bar road.

Scope

  • Clearing
  • Box culvert extensions
  • Earthworks
  • In-situ pavement stabilisation
  • Deep lift asphalt
  • Line marking

Highlights

  • Well managed traffic with high volumes due to only access into and out of Old Bar
  • Complete 4 weeks ahead of schedule
  • UTS and GPS machine control used throughout project.
  • 3000t of asphalt completed