About This Project
Industry Civil
Budget
$1.2M
Contract
2020
Location
Old Bar
Overview
Goldspring was awarded the contract to upgrade the out-dated intersection of Old Bar Road and Saltwater Road. The project involved shoulder widenings, insitu pavement stabilisation and deep lift asphalt. Project was completed 4 weeks ahead of schedule, which minimised disturbance on the extremely busy Old Bar road.
Scope
- Clearing
- Box culvert extensions
- Earthworks
- In-situ pavement stabilisation
- Deep lift asphalt
- Line marking
Highlights
- Well managed traffic with high volumes due to only access into and out of Old Bar
- Complete 4 weeks ahead of schedule
- UTS and GPS machine control used throughout project.
- 3000t of asphalt completed